Central – Wan Chai Bypass and Island Eastern Corridor Link
Graphic Version   Home Site Map Useful Links Contact Us Privacy Policy Important Notices
  • About CWB • Highlights • Works Progress • Public Engagement • CWB Library • Multimedia Gallery
  Home >About CWB>Contract Packaging>Contract No. HY/2011/08 |EN  
  Contract Packaging
 

Introduction

Contract No. HY/2011/08 – Tunnel Buildings, Systems and Fittings, and works associated with Tunnel Commissioning

  • The works in this package mainly include:

 
  • Construction of Tunnel Buildings, i.e. West Ventilation Building (WVB), Middle Ventilation Building (MVB), East Ventilation Building (EVB), East Vent Shaft (EVS) and Administration Building (ADB), including structure and building services;
  • Installation of route-wide tunnel E&M works (including fire services installations);
  • Installation of route-wide TCSS works;
  • Construction of tunnel cladding works;
  • Testing and commissioning.
  • The Tunnel Buildings will be installed with Green Roofs and planting in the periphery to promote a greening environment.

  • The Contract is expected to commence in early 2014 for completion in the end 2017.
 
 