  Works Progress
 
  North Point
 
  Construction Activities
 

Works in North Point District are undertaken by two contracts: a) Tunnel (North Point Section) and Island Eastern Corridor Link Contract (Contract No: HY/2009/19) and b) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning Contract (Contract No: HY/2011/08) 


a) Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No: HY/2009/19) 
This contract includes the construction of a 300-metre-long tunnel section, together with an approach road and modification of a section of Island Eastern Corridor (IEC). Associated works such as landscaped deck, noise barriers, noise semi-enclosures, road drainage and landscaping works are also included in this contract.

b) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning (Contract No: HY/2011/08) 
This contract is for the construction of the Tunnel Buildings in North Point District, i.e. East Ventilation Building (EVB), East Vent Shaft (EVS), Administration Building (ADB), construction of tunnel cladding works, installation of route-wide tunnel electrical and mechanical works as well as the traffic control and surveillance system. The contract scope also includes testing and commissioning works.

 
  Main Temporary Traffic Arrangements
 

To facilitate the construction works in North Point, Temporary Traffic Arrangements will be/have been implemented as follows:

 

a) To facilitate the works of Central – Wan Chai Bypass, temporary traffic arrangements was implemented at Island Eastern Corridor Eastbound since mid September 2020. For more details, please refer to below poster .

 

b) The access connecting Watson Road and Harbour Heights has been reprovisioned and was re-opened from 11:00am on 29 August 2020. For more details, please refer to below leaflet .

 

c) In response to the latest traffic condition at Hing Fat Street and opinions collected from the nearby residents, road improvement works at Hing Fat Street, Wing Hing Street and Gordon Road commenced in mid-August 2020. For more details, please refer to below leaflet .

 

d) Further to a trial run conducted during 5 to 23 September 2019 on the section of Island Eastern Corridor (IEC) westbound between Henrietta Secondary School and Harbour Heights, temporary traffic arrangements on IEC westbound has been implemented from 23 October 2019 to facilitate road works and the installation of remaining noise enclosures. For more details, please refer to below poster .

 




 
 