Works Progress

Causeway Bay

Recent Construction Activities

Works in Causeway Bay District are undertaken by three contracts: a) Tunnel (Causeway Bay Typhoon Shelter Section) Contract (Contract No: HY/2009/15), b) Tunnel (Slip Road 8 Section) Contract (Contract No: HY/2010/08) and c) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning Contract (Contract No: HY/2011/08)


a) Tunnel (Causeway Bay Typhoon Shelter Section) (Contract No: HY/2009/15) 
This contract is for the construction of the tunnel sections underneath ex-Wan Chai Public Cargo Working Area, Causeway Bay Typhoon Shelter and Cross Harbour Tunnel. The contract also includes the construction of a ventilation adit along the bottom part of the eastern breakwater of Causeway Bay Typhoon Shelter. 

 

At the ex-Wan Chai Public Cargo Working Area, the tunnel construction was completed in end-March 2016 and the removal of the temporary reclaimation was completed in end-December 2016.

 

At the mined tunnel section underneath Cross Harbour Tunnel, the excavation works was completed in end-April 2015 and the construction of tunnel structure was completed in October 2015.  (More information...)





b) Tunnel (Slip Road 8 Section) (Contract No: HY/2010/08) 
This contract is for the construction of a 300-metre-long section of tunnel section under the seabed of Causeway Bay Typhoon Shelter (CBTS) and a 150-meter-long slip road tunnel beneath the existing Victoria Park Road and the northern part of Victoria Park. (More information…)

 

At Causeway Bay Typhoon Shelter, construction of tunnel structure was completed. Temporary reclamation works to facilitate the tunnel construction is now being removed.

 

The sea bed would be reinstated after the completion of the construction works in the Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area. 

 

At Victoria Park Road and the northern part of Victoria Park, construction of Slip Road 8 connected to the main tunnel is now in progress.

c) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning (Contract No: HY/2011/08) 

This contract is for the construction of tunnel cladding works, installation of route-wide tunnel electrical and mechanical works as well as the traffic control and surveillance system. The contract scope also includes testing and commissioning works. (More information…) 

 



Main Temporary Traffic Arrangements

To facilitate the construction works under Tunnel (Slip Road 8 Section) Contract (Contract No. HY/2010/08), temporary traffic arrangements has been implemented as follows:

A section of Island Eastern Corridor near Victoria Park Road will be reinstated to its original alignment in stages from August 2017. For more details, please refer to the leaflet.

back to top
UNINTERRUPTED FLOW URBAN GREENING ENVIRONMENTALLY FRIENDLY HARBOUR PROTECTION SPACIOUS VIBRANCY CONNECTION

Share |

You can subscribe to CWB eNews.


CAPTCHA Image Reload Image

   
Graphics represent an artist’s impression of the works
concerned only. They are not drawn to scale and have
been edited and processed with computerized
imaging techniques.